This page presents a short time-line of the UGTag and PolUkr projects
|
Activity |
Start Time |
End |
| Project start | 01-01- 2009 | |
| Initial design, analyzing user requirements | 01-01-2009 | 01-04-2009 |
| Reorganizing UGS dictionary | 01-02-2009 | 30-09-2009 |
| MTE v4 specifications | 01-06-2009 | 30-10-2009 |
| Implementation | 01-02-2009 | 30-10-2009 |
| Pre-release testing | 30-10-2009 | 15-11-2009 |
| end of project | 30-11-2009 (planned) |
|
Activity |
Start Time |
End |
| Project start | 01-04- 2009 | |
| Initial design, analyzing user requirements | 01-04-2009 | 01-07-2009 |
| Core implementation | 01-06-2009 | 01-09-2009 |
| Sentence alignment interface implementation | 01-08-2009 | 30-10-2009 |
| Corpus preparation (text scanning, recognizing, spellchecking) | 01-04-2009 | 30-10-2009 |
| Pre-release testing | 30-10-2009 | 15-11-2009 |
| end of project | 30-11-2009 (planned) |
Last updated, 17 October, 2009, by Andriy Mykulyak. See also UGTag and project PolUkr